Right wing update…


Quick update for last few days of work on my 650 build – Next is to check for final tolerances and rivet the wing skins so wing # 2 is doneski …kind of and start with fuselage

  • top skin is final drilled and cleco’ed
  • nose skin drilled to 30 size and ready for final drilling 
  • fuel tank installed with fuel sender installed from top of the wing 
  • Next is to check for final tolerances and rivet the wing skins so wing # 2 is doneski …kind of and start with fuselage-
  • Wing top skin all drilled and cleco’ed to final size
  • Botton wing all drilled and aligned flat and ready for final drilling
  • Nose ribs installed